Question: A small project is composed of seven activities, whose time estimates are listed in the table below: A small project is composed of seven activities,
A small project is composed of seven activities, whose time estimates are listed in the table below: A small project is composed of seven activities, whose time estimates are
listed in the table below:
i Draw the network diagram of activities in the project.
ii Find the expected duration and variance for each activity. What is the
expected project length?
iii Calculate the variance and standard deviation of the project length.
What is the probability that the project will be completed atleast
weeks earlier than expected time.
Activity i j Estimated Duration Weeks
Optimistic Most Likely Pessimistic
i Draw the network diagram of activities in the project.
ii Find the expected duration and variance for each activity. What is the expected project length?
iii Calculate the variance and standard deviation of the project length. What is the probability that the project will be completed atleast weeks earlier than expected time.
Z
Prob.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock