Question: A small project is composed of seven activities, whose time estimates are listed in the table below: A small project is composed of seven activities,

A small project is composed of seven activities, whose time estimates are listed in the table below: A small project is composed of seven activities, whose time estimates are
listed in the table below:
i) Draw the network diagram of activities in the project.
ii) Find the expected duration and variance for each activity. What is the
expected project length?
iii) Calculate the variance and standard deviation of the project length.
What is the probability that the project will be completed atleast 4
weeks earlier than expected time.
Activity (i j) Estimated Duration (Weeks)
Optimistic Most Likely Pessimistic
12117
13147
14228
25111
352514
46258
563615
i) Draw the network diagram of activities in the project.
ii) Find the expected duration and variance for each activity. What is the expected project length?
iii) Calculate the variance and standard deviation of the project length. What is the probability that the project will be completed atleast 4 weeks earlier than expected time.
Z 0.671.001.332.00
Prob. 0.25140.15870.09180.0228
 A small project is composed of seven activities, whose time estimates

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!