Question: A small sample of your project's PERT calculations is shown here. Activity 2 is particularly important to the project, and your stakeholders are asking for
A small sample of your project's PERT calculations is shown here. Activity 2 is particularly important to the project, and your stakeholders are asking for a confidence level for this activity. You tell them there is a 95.44 percent chance of completing activity 2 within how many days?
Activity | Optimistic | Pessimistic | Likely Expected Value |
1 | 10 | 14 | 12 |
2 | 20 | 30 | 23 |
3 | 3 | 3 | 3 |
a.
Between 21 and 25 days
b.
Between 13 and 33 days
c.
Between 18 and 28 days
d.
Between 23 and 28 days