Question: A small sample of your project's PERT calculations is shown here. Activity 2 is particularly important to the project, and your stakeholders are asking for

A small sample of your project's PERT calculations is shown here. Activity 2 is particularly important to the project, and your stakeholders are asking for a confidence level for this activity. You tell them there is a 95.44 percent chance of completing activity 2 within how many days?

Activity

Optimistic

Pessimistic

Likely Expected Value

1

10

14

12

2

20

30

23

3

3

3

3

a.

Between 21 and 25 days

b.

Between 13 and 33 days

c.

Between 18 and 28 days

d.

Between 23 and 28 days