Question: A small software developement project at Krishna Dhir's firm has five major activities. The times (in days) are estimated and provided in the table below:

A small software developement project at Krishna Dhir's firm has five major activities. The times (in days) are estimated and provided in the table below:
Please show the calculations A small software developement project at Krishna
Immediate Predecessor a Activity A B C D E m 5 5. 7 5 3 2 3 4 2 3 b 8 9 10 14 3 A B a) The expected completion time for this project is days (enter your response as a whole number). b) The project variance of completion time is days (enter your responso as a whole number). c) The probability that this projectbe can bo completed in 17 days or less is (keep two decimal places) d) The probability that it will take more than 17 days to complete this projectbe is (hoop two decimal places) ) The duo date that yields a 98% chance of completion is days (koup two decimal places) Enter your answer in the edit fields and then click Check Answer. Calculator Ask My Instructor Print Clear All Check

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!