Question: A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below. ACTIVITY IMMEDIATE

A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below. ACTIVITY IMMEDIATE PREDECESSOR a m b
A -2814
B -71319
C A 71019Find the expected completion time for this project.
The expected completion time for this project is
enter your response here (enter your response as a whole number).