Question: A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below: Immediate Predecessor

A small software development project at Krishna
A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below: Immediate Predecessor a m Activity B C D E 2 3 4 b 8 9 10 14 3 5 6 7 5 3 B 2 3 a) The expected completion time for this project enter your response as a whole number) b) The project variance value of completion time is (enter your response as a whole number)