Question: A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below. ACTIVITY IMMEDIATE
A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below.
| ACTIVITY | IMMEDIATE PREDECESSOR | a | m | b | ||
| A | 1 | 7 | 13 | |||
| B | 4 | 7 | 10 | |||
| C | A | 5 | 8 | 11 | ||
| D | B | 2 | 5 | 8 | ||
| E | C | 4 | 4 | 4 | ||
Part 2
a) Find the expected completion time for this project.
The expected completion time for this project is:
(enter your response as a whole number).