Question: A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below. IMMEDIATE PREDECESSOR

A small software development project at Krishna

A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below. IMMEDIATE PREDECESSOR ACTIVITY a m b 1 4 SOLO 3 A B D 9 13 15 8 A 2 5 B 4 3 7 3 16 3 m C a) Find the expected completion time for this project. The expected completion time for this project is (enter your response as a whole number)