Question: A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below: Activity Immediate
A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below:
| Activity | Immediate Predecessor | a | m | b |
| A | minus |
| 2 | 5 | 8 |
| B | minus |
| 3 | 6 | 9 | ||
| C | A | 4 | 7 | 10 |
| D | B | 2 | 5 | 14 |
| E | C | 3 | 3 | 3 |
Part 2
a) The expected completion time for this project is
enter your response here
(enter your response as a whole number).
Part 3
b) The project variance value of completion time is
enter your response here
(enter your response as a whole number).