Question: A snap back time study was conducted on a tablet compressor machine where machine time is completely automated and a full time worker requires some

A snap back time study was conducted on a tablet compressor machine where machine time is completely automated and a full time worker requires some manual tasks. Necessary information is as follows;

Pieces produced per cycle = 2

Average OT for manual tasks time = 5.75 min

Average OT for machining time (power feed) = 4 min

Performance rating = 105 %

Machine time allowance = 5%Manual task allowance = 10%

Cycle time = Manual time + Machining time

19. A burger restaurant opens its business 12 hours a day but with 2 hour downtime for cleaning. The demand is 600 burgers in a day. What is the takt time?

a. 0.5 minutes per burger

b. 1.0 minutes per burger

c. 1.2 minutes per burger

d. 4.2 minutes per burger

22. If operating time of a machine is 250 minutes and total break down time is only 12 minutes, what is the MTTR?

a. 40 minutes

b. 50 minutes

c. 60 minutes

d. Cannot be calculated with the information provided

23.The setup time for a batch of 300 products is 30 minutes while the production time is 15 minutes for each product. What will be the product manufacturing time for each unit?

a. 15.1 minutes

b. 12 minutes

c. 22 minutes

d. 14 minutes

25. The setup time for a batch of 250 products is 30 minutes while the production time is 5 minutes for each product. If the batch size goes up to 400, what will be the effect on product manufacturing time?

a. Increase by 0.04 minutes

b. Decrease by 0.055 minutes

c. Increase by 0.02 minutes

d. Decrease by 0.045 minutes

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!