Question: A software company can develop a cybersecurity system for $260,000 and it will cost $25000 per month. A vendor promises that you can purchase the
A software company can develop a cybersecurity system for $260,000 and it will cost $25000 per month. A vendor promises that you can purchase the system for $16,000, but you will have a monthly fee of $50,000. If the duration of the project will exceed than months, its better to build the solution. 8 months 9.76 months 10 months 9 months