Question: A software development project has $ 1 0 0 K budget and a timeline of 6 months. After 3 months, there actual costs is 6
A software development project has $K budget and a timeline of months. After months, there actual costs is K and the project is complete. Am I over or under budget? Behind or ahead of schedule? what is the earned value, estimate to complete and variance at completion? show this in a table.