Question: A software development project is experiencing repeated scope changes requested by stakeholders, causing delays and cost overruns. The project manager needs to assess whether these
A software development project is experiencing repeated scope changes requested by stakeholders, causing delays and cost overruns. The project manager needs to assess whether these changes align with business objectives while keeping the project within schedule and budget. In which process group and knowledge area should the project manager primarily focus? Monitoring and Controlling - Scope Management Excuting -Schedule Mansgement Initiating - Stakeholder Management Closing - Procurement Management