Question: A software development team is halfway through a project to launch a new mobile app. During their weekly review, the project manager notices that the

A software development team is halfway through a project to launch a new mobile app. During their weekly review, the project manager notices that the project is behind schedule on several key tasks. To address this, the manager compares actual progress against the project plan and decides on corrective actions to bring the project back on track. Which project management process group is the manager primarlhy using? Initiating Monitoring and Controlling Planning Executing