Question: A software development team is starting a new project to build a mobile banking app. During the initial phase, the project manager emphasizes defining the
A software development team is starting a new project to build a mobile banking app. During the initial phase, the project manager emphasizes defining the project's objectives, identifying deliverables, and creating a detailed schedule before any coding begins. Which project management process group does this phase primarily represent?Monitoring and ControllingCosingExecutingPLAnting