Question: A software development team is using the Agile development life cycle model for a new project. During a sprint, they realize that a feature they

A software development team is using the Agile development life cycle model for a new project.
During a sprint, they realize that a feature they are working on is more complex than initially thought and cannot be completed within the current sprint.
What should the team do?
answer
Break the feature down into smaller tasks and distribute them over the next few sprints.
Move on to the next feature and return to the complex feature in a future sprint.
Drop the feature from the project.
Continue working on the feature past the end of the sprint until it is completed.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!