Question: A software project is very close to its deadline,but is running behind schedule.Without intervention it is expected to be late and this will not be
A software project is very close to its deadline,but is running behind schedule.Without intervention it is expected to be late and this will not be acceptable. The project manager has been told that management are prepared to provide additional resources (funds and/or software developers) to get the project completed on time.
The project manager is considering options to get the project completed by the deadline.
One option is to assignadditional software developers to the tasks on the critical paths.
- Is this a good option? Discuss the advantages and disadvantages of this option.
(2 marks)
Describe another option that the project manger should consider. Discuss the advantages and disadvantages of this alternative approach.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock