Question: A spending variance is calculated by comparing the: A) The difference between the actual amount of the cost and how much a cost should have
A spending variance is calculated by comparing the:
A) The difference between the actual amount of the cost and how much a cost should have been, given the actual level of activity
B) Planning budget to the felcible budget
C) Planning budget to the actual results
D) Static budget to the actual results