Question: A spending variance is calculated by comparing the: Multiple Choice planning budget to the flexible budget. planning budget to the actual results. static budget to

A spending variance is calculated by comparing the: Multiple Choice planning budget to the flexible budget. planning budget to the actual results. static budget to the actual results. flexible budget to the actual results