Question: A standard work year is 2 , 4 0 0 hours at the Luther Mill and it takes about 2 hours to fill a customer

A standard work year is
2
,
4
0
0
hours at the Luther Mill and it takes about
2
hours to fill a customer order. Last year saw
1
8
,
0
0
0
customer orders at the mill and the manager has a new Ford F
-
1
5
0
in mind as a company car, so he hopes that there is an increase of
1
0
%
in customer orders for next year. If the manager hires
1
5
workers, what is the capacity cushion?
A
)
5
4
.
2
%
B
)
8
.
3
%
C
)
4
5
.
8
%
D
)
9
1
.
7
%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!