Question: A stud wall 4 ' high and 1 5 0 0 ' long was estimated at a labor cost of $ 1 . 5 0
A stud wall high and long was estimated at a labor cost of $ per square foot.
The project is now complete, and labor hours have been expended to date at a cost of $ per hour. Using the rate of production, what is the estimated projected cost savings or overrun for labor at completion?