Question: A subcontractor signed a contract to excavate 5 8 6 0 meter of trench in hard clay for an undeground cable. The trench will be
A subcontractor signed a contract to excavate meter of trench in hard clay for an undeground cable. The trench will be cm wide and average depth will be cm Rubber tire trenching
machine with one labor in addition to the operator will be used with productivity rate meter min Assume min for effective hour for expected delay and other conditions. The duration required to excavate the whole quantity is near to
a days
b days
cdays
d days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
