Question: A subcontractor signed a contract to excavate 5 8 6 0 meter of trench in hard clay for an undeground cable. The trench will be

A subcontractor signed a contract to excavate 5860 meter of trench in hard clay for an undeground cable. The trench will be 30 cm wide and average depth will be 165 cm. Rubber tire trenching
machine with one labor in addition to the operator will be used with productivity rate 1.5meter min Assume 45 min for effective hour for expected delay and other conditions. The duration required to excavate the whole quantity is near to?
a)11 days
b)12 days
c)15days
d)16 days