Question: A subcontractor submits a bid to a general contractor for work on a project. Promissory estoppel will not be present if ( select all that
A subcontractor submits a bid to a general contractor for work on a project. Promissory estoppel will not be present if select all that apply:
The subcontractor's quote contains an obvious mistake
The general contractor delays unreasonably in awarding the work
The general contractor shops the bids.
The general contractor tries to add additional or changed terms to the contract