Question: A subtask can be subdivided into two work packages to be performed by the same person but cost and duration estimates would not be improved.

A subtask can be subdivided into two work packages to be performed by the same person but cost and duration estimates would not be improved. Which of the following is true of this scenario?

Select one:

a. Divide the subtask if the work packages are on the critical path.

b. Divide the subtask because the work packages improve task assignment.

c. Do not divide the subtask if it increases risk identification rates.

d. Do not divide the subtask if it increases reporting and control requirements.