Question: A supply-constrained process involves 3 tasks with activity times of 5 minutes/unit, 8 minutes/unit, and 5 minutes/unit, respectively. Currently one worker is assigned to each

  1. A supply-constrained process involves 3 tasks with activity times of 5 minutes/unit, 8 minutes/unit, and 5 minutes/unit, respectively. Currently one worker is assigned to each task. What is the labor utilization?
  1. 25%
  2. 50%
  3. 75%
  4. None of the above