Question: A surface infiltration basin will be constructed to manage 1 in ( 2 5 mm ) of runoff over 1 - ha drainage area. The
A surface infiltration basin will be constructed to manage in mm of runoff over ha drainage area.
The surrounding soils are classified as loamy sand with an infiltration rate of inh The basin filling
time is designed as h and the maximum holding time is h Assume that sediment and biogrowth
clogging factor is
A For side slopes of : and a bottom lengthtowidth ratio of : find the dimensions of the infiltration
basin.
B Find the volume of sand necessary for the bottom fill of the infiltration basin.