Question: A T= 20 T= 10 C T= 10 D E F T= 10, T= 20, T=5 The figure shows the network diagram of a

A T= 20 T= 10 C T= 10 D E F T=

A T= 20 T= 10 C T= 10 D E F T= 10, T= 20, T=5 The figure shows the network diagram of a project along with the activity durations (T). In this project what is the earliest start time for activity E? (Only enter the number, do not try to enter the unit)