Question: a) Table 1 below is the information available about a large project. Draw the network diagram for this project and complete the table 2. Determine

a) Table 1 below is the information available

a) Table 1 below is the information available about a large project. Draw the network diagram for this project and complete the table 2. Determine the project's critical path and duration of the expected completion time of the project. Activity Description Immediate Time Predecessor(s) (Weeks) 5 B 4 B 6 D B 6 E B 4 F D 2 B 6 7 1 EG 8 B 4 K 8 L F.H.K 4 M L 6 N 1 8 o N 2 N 5 C 9 R M.O.P. 3 S R 7 Table 1 (8 marks]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!