Question: A table has 4 legs and a top. The top has 1 2 wood slats. Lead time for wood slats is 3 weeks. Lead time
A table has legs and a top. The top has wood slats. Lead time for wood slats is weeks. Lead time for all other components is week. Nails and screws aren't added to the BOM. What is most probably the LT for nails and screws?
day because those can be bought from a hardware store
Can't tell!
because hardware is usually kept in stock and replenished frequently in these situations
week