Question: A task has a slack of 6 , an EF of 1 5 , and a duration of 5 . Its LS is Multiple Choice

A task has a slack of 6, an EF of 15, and a duration of 5. Its LS is
Multiple Choice
01:31:23
10
13
16
19
21
can't be determined
 A task has a slack of 6, an EF of 15,