Question: A task has an optimistic completion time of 6 days, a most likely time of 12 days, and a pessimistic time of 15 days. The
A task has an optimistic completion time of 6 days, a most likely time of 12 days, and a pessimistic time of 15 days. The expected task duration 1
A. 10 days
CB 105 days
OC It days
D.11.5 days
CE 12 days