Question: A Task time estimates for the modification of an assembly line at Robert Kason's Ontario factory area follow Time Immediate Activity (in hours) Predecessors 50

 A Task time estimates for the modification of an assembly line

A Task time estimates for the modification of an assembly line at Robert Kason's Ontario factory area follow Time Immediate Activity (in hours) Predecessors 50 B 7.5 40 A D 70 BC E 4.5 B, C F 65 D G 40 EF This exercise contains any parts de bande d) Use the multipoint curve drawing tool five times, draw a Gantt chat for activities through of the project based on the early times