Question: A team is working on a project with 1 2 0 use case points. Each team member completes 2 story points in one week. The

A team is working on a project with 120 use case points. Each team member completes 2 story points in one week. The velocity of the team is 20 use case points, what 's the size of the team? Assume the team is using a sprint of two weeks.
1.
Ten (10)
2.
Five (5)
3.
Six (6)
4.
Twnety five (25)