A team of 6 bricklayers is about to start on a new building. According tto the schedule
Fantastic news! We've Found the answer you've been seeking!
Question:
A team of 6 bricklayers is about to start on a new building. According tto the schedule they have 12 days to complete the job. If 2 of them get sick just before they start,
Required:
How many days would the remaining 3 bricklayers need to complete the job?