Question: A team will be working on a project with requirements that evolve over time. The stakeholders accept flexibility over predictability. The team values transparency and
A team will be working on a project with requirements that evolve over time. The stakeholders accept flexibility over predictability. The team values transparency and provides honest timeline and budget to their stakeholders. Which planning strategy should be applied to this scenario? Pick one Detailed release plan High level release plan No release plan Rolling wave release plan
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
