Question: A technique that uses optimistic, pessimistic, and realistic time to calculate the expected time for a particular task best defines a) Gantt. b) Computer Aided
A technique that uses optimistic, pessimistic, and realistic time to calculate the expected time for a particular task best defines a) Gantt. b) Computer Aided Software Engineering (CASE). c) Program Evaluation Review Technique (PERT). d) flowcharting