Question: A technology firm has assigned a project manager for each of the five new - product teams. The managers, as well as the project team

A technology firm has assigned a project manager for each of the five new-product teams. The managers, as well as the project team members, work on the projects on a full-time basis. The structure being used is ______________ organization.
Group of answer choices
strong matrix
balanced matrix
functional
weak matrix
projectized