A ten year project costs $400,900 and produces $68,725 cash flows at the end of each of
Fantastic news! We've Found the answer you've been seeking!
Question:
A ten year project costs $400,900 and produces $68,725 cash flows at the end of each of the following ten years.If the discount rate is 12%, should this project be accepted based on the profitability index rule? Why or why not?
Points:1
- No; because the PI is 0.97
- No; because the PI is 1.03
- Yes; because the PI is 0.97
- Yes; because the PI is 1.03