Question: A textile development project needs a specialized resource to work for 900 hours. The company has decided to outsource these hours. Because of internal policies,
A textile development project needs a specialized resource to work for 900 hours. The company has decided to outsource these hours. Because of internal policies, all potential service providers must be given the same information about the requirements. Which action should the project manager take to ensure this? Group of answer choices Conduct a bidder conference with the service providers. Hold direct negotiations with each service provider. Add each of the service providers to the stakeholder register. Ensure the procurement management plan is sent to each service provider