Question: a ) The expected ( estimated ) time for activity C is 1 2 weeks. ( Round your response to two decimal places. ) Part

a) The expected(estimated) time for activity C is
12 weeks. (Round your response to two decimal places.)
Part 3
b) The variance for activity C is
2.78 weeks. (Round your response to two decimal places.)
Part 4
c) Based on the calculation of the estimated times, the critical path is
A - B - E - F - H - J - K
.
Part 5
d) The estimated time for the critical path is
44.34 weeks. (Round your response to two decimal places.)
Part 6
e) The activity variance along the critical path is
25.39 weeks. (Round your response to two decimal places.)
Part 7
f) Using the standard normal tableLOADING..., the probability that Mbeki Construction will finish the project in 40 weeks or less is
enter your response here. (Enter as a probability and round your response to three decimal places.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock