Question: a ) The expected ( estimated ) time for activity C is 1 2 weeks. ( Round your response to two decimal places ) b
a The expected estimated time for activity is weeks. Round your response to two decimal places
b The variance for activity is weeks. Round your response to two decimal places.
c Based on the calculation of the estimated times, the critical path is AC F H J K
d The estimated time for the critical path is weeks. Round your response to two decimal places.
e The activity variance along the critical path is weeks. Round your response to two decimal places
f Using the standard normal table, the probability that Hopkins Hospitality will finish the project in weeks or less is Enter as a probability and round your response to three decimal places