Question: a ) The expected ( estimated ) time for activity C is 1 3 . 3 3 1 3 . 3 3 weeks. ( Round
a The expectedestimated time for activity C is
weeks. Round your response to two decimal places.
Part
b The variance for activity C is
weeks. Round your response to two decimal places.
Part
c Based on the calculation of the estimated times, the critical path is
A C F H J K
Part
d The estimated time for the critical path is
weeks. Round your response to two decimal places.
Part
e The activity variance along the critical path is
weeks. Round your response to two decimal places.
Part
f Using the standard normal table
LOADING...
the probability that Hopkins Hospitality will finish the project in
weeks or less is
Enter as a probability and round your response to three decimal places.
I DONT UNDERSTAND HOW TO FIND THE probability from the chart. How do obtain the
zxuo
square root of
How do I get the O from looking at standard normal table
Z
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock