Question: a) The expected (estimated) time for activity C is 14 weeks (Round your response fo two decima places b) The varlance for activiny C is

a) The expected (estimated) time for activity C is 14 weeks (Round your response fo two decima places b) The varlance for activiny C is 278 weeks. (Round your response to two decimal places) c) Based on the calculation of the estimated times, the critical path is ADJKACGJKABEFHJKACFHJKABEGJKABEFIKACFIK