Question: a) The expected (estimated) time for activity C is ____ weeks (Round 2 decimals) b) Variance for activity C is ____ weeks. c) Based on
a) The expected (estimated) time for activity C is ____ weeks (Round 2 decimals)
b) Variance for activity C is ____ weeks.
c) Based on the calculation of the estimated times, the critical path is ______
d) The estimated time for the critical path is _____ weeks
e) the activity variance along the critical path is ____ weeks
f) using the standard normal tabls, the probability that Hopkins Hospitality will finish the project in 36 weeks or less is ____
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
