Question: a) The expected (estimated) time for activity ( mathrm{C} ) is weeks. (Round your response to two decimal place: b) The variance for activity (

a) The expected (estimated) time for activity \( \mathrm{C} \) is weeks. (Round your response to two decimal place: b) The variance for activity \( \mathrm{C} \) is weeks. (Round your rosponse to two