Question: A The following table provides the information necessary to construct a project network and project crash data. Crash the project as much as possible. Maximum

A The following table provides the information
A The following table provides the information necessary to construct a project network and project crash data. Crash the project as much as possible. Maximum allowance for crash cost is $800/day. Activity Predecessor Normal Time Crash Time Crash Cost/day 7 A 9 $500 A 5 $300 D $700 E 5 $600 F DE 2 $800 7 7 B 4 B 4 3 OSHA is The Occupational Safety and Health Administration. It is an agency of the United States government. Summarily described, this agency is responsible for workplace safety in the U.S