Question: a) The unit network for small project involve 19 units, calculate the duration of project if there are only one crew? 3 8 15 12

a) The unit network for small project involve 19
a) The unit network for small project involve 19 units, calculate the duration of project if there are only one crew? 3 8 15 12 4 16 16 7 23 23 28 + 5 23 a 4 0 4 12 23 C 8 e 11 4 12 12 23 Select one: a. 104 O b. 97 O c. 226 O d. 223