Question: A time analyst observed a job for which the work methods have just been changed. The job is divided into four work elements. The element
A time analyst observed a job for which the work methods have just been changed. The job is divided into four work elements. The element times for the first five cycles, recorded on a continuous basis, are shown in the following table with a performance rating (RF) for each element
Cycle Times:
| Element: | 1 | 2 | 3 | 4 | 5 | RF |
| 1 | 0.50 | 3.30 | 5.70 | 8.20 | 10.85 | 1.10 |
| 2 | 0.70 | 3.45 | 5.95 | 8.55 | 11.10 | 1.20 |
| 3 | 1.45 | 4.05 | 6.50 | 9.25 | 11.75 | 1.20 |
| 4 | 2.75 | 5.25 | 7.60 | 10.35 | 13.00 | 0.90 |
A. Calculate the normal time for this job
B. Calculate the standard time for this job, assuming that the allowance is 20%
C. What is the appropriate sample size for estimating the time for element 2 within +/-10% of the true mean with 95% confidence?
D. What is the sample size needed for a precision of +/-5%?
Step by Step Solution
There are 3 Steps involved in it