Question: A time analyst observed a job for which the work methods have just been changed. The job is divided into four work elements. The element

A time analyst observed a job for which the work methods have just been changed. The job is divided into four work elements. The element times for the first five cycles, recorded on a continuous basis, are shown in the following table with a performance rating (RF) for each element

Cycle Times:

Element: 1 2 3 4 5 RF
1 0.50 3.30 5.70 8.20 10.85 1.10
2 0.70 3.45 5.95 8.55 11.10 1.20
3 1.45 4.05 6.50 9.25 11.75 1.20
4 2.75 5.25 7.60 10.35 13.00 0.90

A. Calculate the normal time for this job

B. Calculate the standard time for this job, assuming that the allowance is 20%

C. What is the appropriate sample size for estimating the time for element 2 within +/-10% of the true mean with 95% confidence?

D. What is the sample size needed for a precision of +/-5%?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!