Question: A time series with forecast values is presented in the following table. The actual value of November is announced as 8.1. Calculate the mean absolute
A time series with forecast values is presented in the following table. The actual value of November is announced as 8.1. Calculate the mean absolute deviation (MAD) for the forecast in the period from August to November.
_. (Calculate to three decimal places. X.XXX)
| Month | Actual | Forecast |
| July | 5 | |
| August | 11 | 5 |
| September | 13 | 7.4 |
| October | 6 | 9.64 |
| November | 8.184 |