Question: A time study for a plant operation revealed an average observed time of 10 minutes. The worker was rated at ( 80 % ). Using

A time study for a plant operation revealed an average observed time of 10 minutes. The worker was rated at \( 80 \% \). Using an allowance factor of \( 10 \% \), the standard time for the operation i 