Question: A time study is conducted on a process that has three ( 3 ) separate operations. The process involves five ( 5 ) masons placing

A time study is conducted on a process that has three (3) separate operations. The process involves five (5) masons placing 1 cubic yard of concrete for each cycle. Ten cycles of each operation are carried out to improve accuracy. The results of the study are as follows: (SHOW YOUR CALCULATIONS IF POSSIBLE)
Operatior
Total time (seconds) for 10 cycles or repetitions
#1
975
#2
643
#3
917
Overall total
2,535 seconds (for 10 cycles)
The observer assigns the following factors: Allowance =14%, Rating =125%
NOTE THAT IT IS NOT NECESSARY TO PROVIDE VALUES FOR EACH INDIVIDUAL OPERATION - ONLYTHE TOTAL.
a.) Determine a standard time in minutes per cycle for the entire process and record (FOR 1 CYCLE)
the values for the following:
Select time PER CYCLE :
Normal time (seconds)=
Standard time (in minutes)=
 A time study is conducted on a process that has three

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!